Construction is now underway on the Mureau Road / Round Meadow Road Landscape and Hardscape Improvements Project. So that residents can anticipate upcoming activity, the City is making the contractor’s baseline schedule and traffic control plan available below.
Project Schedule
| Notice to Proceed / Project Start | June 29, 2026 |
| Submittals, Review, and Material Procurement | June 29 – July 24, 2026 |
| Mobilization | June 29 – July 3, 2026 |
| Demolition and Clearing | July 6 – July 14, 2026 |
| Underground Drainage Work | July 15 – July 21, 2026 |
| Concrete Construction / Hardscape Work | July 22 – August 12, 2026 |
| Irrigation Work | August 13 – September 16, 2026 |
| Electrical Work | September 8 – October 2, 2026 |
| Landscaping | September 17 – October 22, 2026 |
| Substantial Completion | October 22, 2026 |
| Punch List / Closeout | October 23 – November 13, 2026 |
Traffic Control
Under the traffic control plan, residents can expect lane closures, bike lane closures, and signage throughout the project area. Driveway access will be available during working hours, and access for residents, businesses, and emergency vehicles will remain in place at all times.
School Traffic Considerations
The heaviest construction work — demolition, drainage, and hardscape — is scheduled to wrap up before students return from summer break. Some lane closures and construction activity will continue into the fall for irrigation, electrical, and landscaping work. City staff will coordinate with the contractor to minimize disruption during morning drop-off and afternoon pick-up periods.
Staff will continue to monitor the schedule and will provide updates if conditions change or if traffic control measures are expected to affect school-related traffic routes.